Project
Aether
A bespoke 2,450 sq.ft 3BHK semi-furnished duplexes situated on a prominent 60-ft and 30-ft corner road in Cheran ma nagar. Built with uncompromised material quality, skilled labour, perfect Vaasthu and Manai Adi Sastra adherence, and two-car luxury parking.
StructureRCC Moment Frame & Machine-Cut Masonry
EnvelopeRecessed Balconies & Weather-Shield Plaster
Thermal Delta-4.6°C Solar Differential
Site Datum11°03'12"N 76°59'45"E • Cheran ma nagar
- Location
- Cheran ma nagar, Coimbatore, Tamil Nadu
- Typology
- 3BHK Semi-Furnished Duplex
- Built-up Area
- 2,450 sq.ft (3.3 Cents Plot)
- Year
- 2025
- Status
- Completed
Overview
Engineered on 3.3 cents of corner land, Aether harmonizes spatial abundance with rigorous structural planning. The thoughtfully designed layout features an expansive 16’ × 16’ living hall, two grand 16’ × 16’ master bedrooms, an additional 10’ × 16’ bedroom, a dedicated pooja room, an external utility zone, and covered parking for two full-size luxury vehicles.
Challenge
The corner junction of 60-foot and 30-foot roads required dual-frontage acoustic and visual privacy while ensuring abundant natural cross-ventilation. Furthermore, aligning room dimensions strictly with traditional Manai Adi Sastra benchmarks required zero-tolerance structural grid calibration.
Approach
ASTHIWAR integrated architecture and structural engineering under one hand. We staggered window fenestrations with deep balcony projections, deployed an optimized moment-resisting RC frame to keep living areas column-free, and ensured every space complies with solar and airflow paths for natural cooling.
Materials
- Primary Fe550D TMT Reinforcement Steel
- Solid High-Density Masonry Blocks
- Smooth Slaked Lime Plaster Wash
- First-Quality Teak Joinery & Doors
- Large-Format Vitrified Tile Flooring
- Toughened Glass Balcony Balustrades
- Weatherproof Exterior Emulsion Coatings
Timeline
Design & Vaasthu Alignment
2 Months
Site survey, Manai Adi Sastra grid calibration, concept and structural analysis
Superstructure & Masonry
5 Months
Isolated column footings, RCC moment frame, precision block masonry
Envelope & Finishes
4 Months
Concealed MEP installations, teak joinery, lime plaster, vitrified flooring
Commissioning & Handover
1 Month
750+ quality checklist sign-offs, service testing, turnkey handover in 2025